Knowledge Base Wiki

Search for LIMS content across all our Wiki Knowledge Bases.

Type a search term to find related articles by LIMS subject matter experts gathered from the most trusted and dynamic collaboration tools in the laboratory informatics industry.

Gates of Hirakud Dam
Hirakud Dam is located in Odisha
Hirakud Dam
Location of in Odisha
Official nameHirakud Dam
Location16.5 km from Sambalpur, Odisha
Coordinates21°34′N 83°52′E / 21.57°N 83.87°E / 21.57; 83.87
Construction began1947
Opening date1957
Construction cost1.01 billion Rs in 1953
Dam and spillways
Type of damComposite dam and reservoir
ImpoundsMahanadi River
Height60.96 m (200 ft)
Length4.8 km (3 mi) (main section)
25.8 km (16 mi) (entire dam)
Spillways64 sluice-gates, 34 crest-gates
Spillway capacity42,450 cubic metres per second (1,499,000 cu ft/s)
Reservoir
Total capacity5,896,000,000 m3 (4,779,965 acre⋅ft) (OR) 205.56 tmc ft (effective)
Catchment area83,400 km2 (32,201 sq mi)
Power Station
TurbinesPower House I (Burla): 2 x 49.5 MW, 3 x 37.5 MW, 2 x 32 MW Kaplan-type
Power House II (Chiplima): 3 x 24 MW[1]
Installed capacity347.5 MW[1]
Designations
Official nameHirakud Reservoir
Designated12 October 2021
Reference no.2494[2]

Hirakud Dam is built across the Mahanadi River, about 10 kilometres (6.2 mi) from Sambalpur in the state of Odisha in India. It is the longest earthen dam in the world. Behind the dam extends a lake, Hirakud Reservoir, 55 km (34 mi) long. It is one of the first major multipurpose river valley projects started after India's independence. Hirakud Reservoir was declared a Ramsar site on 12 October 2021.[3]

Bird's-eye view of Hirakud Dam

Construction history

On 15 March 1946, Sir Hawthorne Lewis, the Governor of Odisha, laid the foundation stone of the Hirakud Dam. A project report was submitted to the government in June 1947. Pandit Jawaharlal Nehru laid the first batch of concrete on 12 April 1948.

In 1952, Mazumdar Committee was appointed by the government to oversee the soundness and technical feasibility of the project. The committee envisaged that the project would cost 92.80 crore and the construction of the main dam would be complete by June 1955. It also said that by 1954–55 a total of 1,347,000 acres (545,000 ha) of land would be irrigated and 48,000 kW of electric power would be generated.[4] However, the dam was completed in 1953 and formally inaugurated by Prime Minister Jawaharlal Nehru on 13 January 1957. The total cost of the project was 1,000.2 million (equivalent to 100 billion or US$1.2 billion in 2023) in 1957. Power generation along with agricultural irrigation started in 1956, achieving full potential in 1966.[5]

Technical details

Dyke
Sasan Canal
Technical Details[5]
Total Length 25.79 km (16.03 mi)
Length of Main Dam 4.8 km (3.0 mi)
Artificial Lake 743 km2 (287 sq mi)
Irrigated Area (both crop) 2,355 km2 (235,477 ha)
Area lost in construction of Dam 596 km2 (147,363 acres)
Installed Capacity (Power Generation) 347.5 MW
Cost (in 1957) 1,000.2 million (equivalent to 100 billion or US$1.2 billion in 2023)
Top dam level R.L. 195.680 m (642 ft)
F.R.L/ M.W.L R.L. 192.024 m (630 ft)
Dead storage level R.L. 179.830 m (590 ft)
Total quantity of earth work in Dam 18,100,000 m3 (640×10^6 cu ft)
Total quantity of concrete 1,070,000 m3 (38×10^6 cu ft)
Catchment 83,400 km2 (32,200 sq mi)

Structure

The Hirakud Dam is a man-made structure of earth, concrete and masonry. 10 km (6.2 mi) north of Sambalpur, it is the longest major earthen dam in the world, measuring 25.8 km (16.0 mi) including dykes, and stands across the river Mahanadi. The main dam has an overall length of 4.8 km (3.0 mi)[5] spanning between two hills; the Laxmidungri on the left and the Chandili Dunguri on the right. The dam is flanked by 21 km (13 mi) of earthen dykes on both the left and right sides, closing the low saddles beyond the adjoining hills. The dam and dykes together measure 25.8 km (16.0 mi).[5] It also forms the biggest artificial lake in India,[dubiousdiscuss] with a reservoir holding 743 km2 (287 sq mi) at full capacity, with a shoreline of over 639 km (397 mi). There are two observation towers on the dam one at each side. One is "Gandhi Minar" and the other one is"Jawahar Minar". Both the observation towers present extensive views of the lake.

Power houses

The dam supports two different hydroelectric power houses. Power House I is located at the base (toe) of the main dam section and contains 3 x 37.5 MW Kaplan turbine and 2 x 24 MW Francis turbine generators for an installed capacity of 259.5 MW. Power Station II is located 19 km (12 mi) southeast of the dam 21°21′10″N 83°55′00″E / 21.35278°N 83.91667°E / 21.35278; 83.91667 (Chipilima Power House II) at Chipilima. It contains 3 x 24 MW generators. The entire installed capacity of the dam's power houses is 347.5 MW. Power House I and II were built in three stages. During stage I, four generators were installed at PH I and in stage II, the power channel two and Power House II was constructed. All three generators were installed at PH II along with two more at PH I by 1963. Between 1982 and 1990, the seventh and final generator was installed at PH I.[1]

Purpose

Fisherman at Hirakud Dam
Left Dyke of Hirakud Dam

In the upper drainage basin of the Mahanadi River, centered on the Chhattisgarh Plain, periodic droughts contrast with the situation in the lower delta region where floods may damage crops. The dam was constructed to help alleviate these problems by creating a reservoir and controlling river flow through the drainage system. The dam regulates the flow of the Mahanadi River and produces hydroelectricity through several hydroelectric plants.[6]

The dam helps control floods in the Mahanadi delta and irrigates 75,000 km2 (19×10^6 acres) of land. Hydroelectricity is also generated. The Hirakud Dam regulates 83,400 km2 (20.6×10^6 acres) of Mahanadi's drainage. The reservoir has a storage capacity of 5.818 km3 (1.396 cu mi) with gross of 8.136 km3 (1.952 cu mi).[5]

It drains an area of 133,090 km2 (32.89×10^6 acres), more than twice the area of Sri Lanka.

The project provides 1,556 km2 (384,000 acres) of kharif and 1,084 km2 (268,000 acres) of rabi irrigation in districts of Sambalpur, Bargarh, Bolangir, and Subarnpur. The water released by the power plant irrigates another 4,360 km2 (1.08×10^6 acres) of CCA in Mahanadi delta. The dam can generate up to 307.5 MW of electrical power through its two power plants at Burla, on the dam's right bank and Chiplima, 22 km (14 mi) downstream from the dam. In addition, the project provides flood protection to 9,500 km2 (2.3×10^6 acres) of delta area in district of Cuttack and Puri.

Chiplima has gained prominence as the second hydroelectric project of the Hirakud Dam. A natural fall of 80 to 120 ft (24 to 37 m) in the river Mahanadi is used to generate electricity. The place is mostly inhabited by fishermen, whose deity Ghanteswari is revered in the neighboring area. The state livestock breeding farm and agricultural farm are located here.

Canal system

Hirakud Dam has three canals, namely Bargarh Main Canal, Sason Canal and Sambalpur Canal. Bargarh Main canal has a water discharge rate of 4,000 cubic feet per second (110 m3/s).

Industrial use

Water from Hirakud Dam at a later stage was allocated to various industries, primarily for mineral processing and coal fired thermal power plants in Jharsuguda and Sambalpur districts.[7]

Issues

Siltation

Statistics published by the dam authority show the water holding capacity of the dam has been reduced by 24% due to siltation.[8]

Water conflict

A major conflict for water was reported when over 30,000 farmers gathered around the dam making a human chain, protesting against the allocation of water to the industries and there being no water for the canal system due to a low water level.[9]

Inter-basin water transfer

There have been plans for inter-basin water transfer, as per plans of the water resource dept of Odisha as part of India's ambitious Indian Rivers Inter-link.

Lost temples

These are remnants of temples submerged after the dam was completed in 1957. In the summer season, the receding water of the dam makes the structures become visible. The hidden treasures have finally caught the attention of historians, and steps are being taken to understand the historical significance of these temples, which periodically go under water, only to resurface again. Many temples have been destroyed after 58 years of underwater existence. However, some remain intact.[10][11]

Interest in these lost temples has been rekindled after two stones, etched with writing ('Shila Lekha'), were recovered from what is believed to be the Padmaseni temple of submerged Padmapur village.[12] The temples located inside the reservoir area were part of the then Padmapur, one of the oldest and most populous in the region prior to the dam construction.[10] More than 200 temples were submerged by the dam, nearly 150 temples have either perished or are underwater and about 50 are visible during summer. The lost temples present excellent opportunities for scuba diving enthusiasts to explore the underbelly of Hirakud Dam. The temple are visible to visitors on boat only during the summer months of May and June.

Cattle Island

One of the many islands within Hirakud Reservoir

Cattle Island is located in one of the extreme points of Hirakud Reservoir, a natural wonder. Completely inhabited by wild animals, it is without any trace of humans. It is near Kumarbandh village of Belpahar-Banharpali range which is about 90 km (56 mi) from Sambalpur. It can be reached by launch from Hirakud Dam, it is closer by 10 km (6.2 mi) via the river. The island is a submerged hill, and before the construction of Hirakud Dam it was a developed village. During the resettlement period, villagers left some of their cattle behind; when the dam construction was over, the cattle settled on the hilltop.

With the passage of time the nearby area filled up with the reservoir water, turning the hilltop into an island. Being away from mankind, the cattle are now wild, very swift and not easily caught. Living on a hilltop with dense forest, they are larger than tame cattle, and almost all are white in color. Nearby residents attempt to capture these animals from time to time, but these hunts are rarely successful. Though descended from tame cattle, these animals provide a contrasting picture of this breed of animal returning to life in the wild.[13]

Wildlife

The dam with the channel provides an ideal environment for the wildlife. The Debrigarh wildlife sanctuary is located here.[14] Several species of migratory birds visit the reservoir during winter. Nearly 20-25 species of birds are seen in the reservoir and common among them are common pochard, red-crested pochard, great crested grebe and several others.[15]

People affected by the dam construction

The main purpose of the Hirakud Dam was to check the massive floods that were affecting a large part of coastal Odisha. But, the construction of the dam greatly affected the natives of the western part of Odisha. Nearly 150,000 people were affected by the Hirakud project and nearly 22,000 families were displaced.

In the original estimate, an amount of 120 million (equivalent to 14 billion or US$160 million in 2023) was provided for payment of compensation to the affected people. After revision, the amount was reduced to 95 million (equivalent to 11 billion or US$130 million in 2023) and the total compensation paid to the people was, in reality, only 33.2 million (equivalent to 3.8 billion or US$45 million in 2023). A large number of families were evacuated from their hearth and homes without compensation from 1956 onwards.[16]

Stamps and notes

A commemorative stamp on Hirakud Dam was released on 29 Oct 1979 by the Department of Posts, with denomination 30 paise (0.36¢ US), 3,000,000 stamps issued.[17] A hundred rupee note was issued on 26 December 1960 by RBI Governor H.V.R. Iyengar. The size of this note is 109 mm × 172 mm (4.3 in × 6.8 in). On the back side of this note there are thirteen regional languages along with an image of the Hirakud Dam and Hydro-Electric station.

Hirakud dam in Rs 100 note released in 1967

See also

References

  1. ^ a b c "Hirakud Power System". Odisha Hydro Power Corporation. Archived from the original on 13 September 2010. Retrieved 3 March 2011.
  2. ^ "Hirakud Reservoir". Ramsar Sites Information Service. Retrieved 7 August 2022.
  3. ^ "Tampara Lake". PIB. Retrieved 5 November 2022.
  4. ^ "Report on Hirakud". The Indian Express. 2 March 1953. p. 3. Retrieved 9 February 2018.
  5. ^ a b c d e Hirakud Dam Archived 2 November 2008 at the Wayback Machine
  6. ^ "Mahanadi River". Archived from the original on 24 November 2006. Retrieved 22 September 2006.
  7. ^ "Archived copy". infochangeindia.org. Archived from the original on 14 April 2021. Retrieved 22 May 2022.{{cite web}}: CS1 maint: archived copy as title (link) CS1 maint: unfit URL (link)
  8. ^ "Hirakud reservoir has lost 24 per cent water holding capacity, says latest hydrology survey". The New Indian Express. Retrieved 1 November 2022.
  9. ^ "30,000 farmers demand Hirakud dam water". downtoearth.org.in. Retrieved 18 February 2021.
  10. ^ a b "Temples resurface in Hirakud bed | Bhubaneswar News". The Times of India. 13 July 2014.
  11. ^ "Hirakud". Archived from the original on 27 September 2018. Retrieved 14 July 2014.
  12. ^ "Ancient rock edicts discovered in Odisha | Sambad English". 24 June 2014. Archived from the original on 25 June 2014.{{cite web}}: CS1 maint: unfit URL (link)
  13. ^ Cattle Island
  14. ^ Debrigarh wildlife sanctuary Archived 24 December 2010 at the Wayback Machine
  15. ^ Migratory birds in Hirakud[permanent dead link]
  16. ^ Hirakud dam: Displaced families seek rehabilitation
  17. ^ "Hirakund Dam". Indianpost.com. Retrieved 21 August 2022.

http://www.hirakuddam.com/places-to-go/